Section 48: selling the Energy Credit (legacy ITC)
The original investment tax credit. New projects now use §48E, but §48 still covers property that began construction before 2025, and geothermal heat pumps until 2035.
Verified · Instructions for Form 3468 (2025)
At a glance · §48
- What it rewards
- A percentage of the basis of energy property (solar, fuel cells, storage, geothermal, small wind, waste energy recovery, biogas and others) placed in service in the year.
- Type
- Investment credit (ITC): a percentage of cost, claimed once
- Rate
- 6% base; 30% if prevailing wage and apprenticeship requirements are met or the project is under 1 MW; bonus adders where their requirements are met.
- Credit period
- One-time credit in the placed-in-service year; five-year recapture period.
- Claimed on
- Form 3468, Part VI, carried to Form 3800
- Transferable?
- Yes, under §6418.
- Status
- Legacy projects only For most property, construction must have begun before 1 January 2025; new projects use §48E. Ground-source (geothermal) heat pump property is the main exception: construction must begin before 1 January 2035.
- Key dates
- : Last day to begin construction under §45 and most of §48
- : §48 geothermal heat pumps: construction must begin before 2035
- Last verified
Who still earns it
The §48 energy credit is a percentage of the basis of energy property placed in service during the year: solar, fuel cells, energy storage, geothermal, small wind, waste energy recovery, qualified biogas, microgrid controllers and others listed in the statute[1].
For most of that property, construction must have begun before 1 January 2025[1]. Projects that started later use the technology-neutral §48E. The main exception is ground-source (geothermal) heat pump property, which stays under §48 if construction begins before 1 January 2035[1].
So in 2026, §48 credits for sale typically come from projects that began construction before 2025 and were placed in service in 2025 or 2026.
Rate and bonus amounts
The energy percentage is 6%, or 30% where the project meets the prevailing wage and apprenticeship requirements or is under 1 MW[1]. Energy-community and domestic-content bonuses can add to that where their own requirements are met. A buyer must receive a proportionate share of every bonus amount[2].
Selling it
For a small solar project, see selling a small solar tax credit.
- Register the property with the IRS after it is placed in service; each property needs its own number[3]. Allow at least 120 days before the return’s due date[4].
- Claim on Form 3468, Part VI, which has its own sections for each type of energy property[5], and report the transfer in Form 3800, Part III, column (f)[6].
- Attach the transfer election statement to the original return[7].
What buyers ask for on a §48 deal: proof that construction began before 2025 (or before 2035 for heat pumps); cost-basis support, usually a cost-segregation report; placed-in-service evidence; prevailing wage and apprenticeship records for the 30% rate; and bonus evidence.
Recapture. If the property is sold or stops qualifying during the five-year recapture period, the buyer bears the recapture and the seller must tell the buyer[8][9]. Expect the buyer to ask for an indemnity, insurance or both, and expect investment credits to price a few cents below production credits.
Common mistakes
- Filing in Part V. Part V of Form 3468 is §48E; §48 belongs in Part VI[5].
- No begin-construction file. For a project placed in service in 2025 or later, the begin-construction evidence is what keeps it under §48 at all.
- Late or amended-return elections, which are not allowed[7].
Frequently asked questions
Are §48 credits transferable?
Yes. The energy credit determined under §48 is an eligible credit under §6418[8].
Which part of Form 3468 is used for a §48 credit?
Part VI, “Energy Credit Under Section 48”[5].
Does the foreign-entity transfer bar apply to §48?
The statutory bar on transfers to specified foreign entities names §§45Q, 45U, 45X, 45Y, 45Z and 48E, not §48[8].
Market price
About $0.895 on average in 2026; $0.92 to $0.95 for investment-grade sellers. Recapture and basis risk explain the discount to production credits.[Cenet Capital]
Market estimate, not an offer. Prices move with buyer demand, deal size, seller credit quality, insurance and foreign-entity exposure. Run your own figures in the Credit Value Estimator, or compare every published report on the prices page.
Deadlines for §48
- Last day to begin construction under §45 and most of §48Facilities and most energy property must have begun construction before 1 January 2025 to use the legacy credits. Later projects use §45Y or §48E.
- §48 geothermal heat pumps: construction must begin before 2035Ground-source heat pump property remains eligible under §48 if its construction begins before 1 January 2035.
Sources
- 26 U.S.C. § 48 — Energy credit
- 26 CFR § 1.6418-1 — Transfer of eligible credits (definitions)
- 26 CFR § 1.6418-4 — Additional information and registration
- Register for elective payment or transfer of credits (page updated 12 Aug 2026)
- Instructions for Form 3468 (2025)
- Instructions for Form 3800 (2025)
- 26 CFR § 1.6418-2 — Rules for making transfer elections
- 26 U.S.C. § 6418 — Transfer of certain credits
- 26 CFR § 1.6418-5 — Special rules (excessive credit transfer, recapture)
- Tax credit price calculator: what is your credit worth in cash? (7 Oct 2026)
- 26 U.S.C. § 45 — Electricity produced from certain renewable resources